Tuesday, March 27, 2012

Week #4

UW-Marinette & Kenny worked with us for the week to continue progress on the house.

One thing to note as I post these photos, is that we're shifting right now. Nicole Spade is leading groups in the morning from 7am-1pm, and I'm leading groups from 1pm-7pm. It's pretty cool to walk into the house every day and see progress happen "over night."

We finally have all the drywall up, and every room has gone through almost all 3 stages of mudding. Lots of skimming, sanding, and priming for next week! And then bring on the paint!

A great week!

(missing photos of kevin!)


Casey & Jess work in the hallway



Nick & Jon scoring drywall


Kenny & Kelsey finishing up the drywall in the bathrooms!



Derek & Kayler working on the upstairs bedrooms



Jess & Nikki skim the master bedroom.


Upstairs Bathroom


Stairway to the second floor!


Bathroom & under stairway closet